Method

Ninety percent of a coating job happens before any colour goes down.

Anyone can roll resin onto concrete. What separates a floor that lasts from one that peels is the preparation nobody photographs and the cure times nobody wants to hear.

Full sequence

Seven stages, in order, every time.

  1. Assess the slab

    Age, finish, hardness, existing coatings or sealers, oil contamination, cracks, control joints, drain slope and edge conditions. On below-grade and newer slabs, a moisture reading is taken before a system is committed to.

  2. Write the scope

    You get the coating system, the layer build, the prep method, the finish selection, the square footage and a price range in writing. If something might change once grinding exposes the slab, that gets named up front rather than appearing as a surprise later.

  3. Contain and protect

    Poly barriers, masking on walls, door tracks and thresholds, and vacuum extraction on every grinder. Concrete dust travels much further than people expect, and it is far cheaper to contain it than to clean it.

  4. Diamond grind

    Planetary grinders open the concrete to the profile the coating manufacturer specifies. Tooling is matched to slab hardness. Edges and corners are ground separately with a hand grinder, because an unground perimeter is the first place a floor fails.

  5. Repair, then re-grind

    Cracks, spalls, pop-outs and joints are filled with a rigid or semi-rigid repair material depending on whether the joint needs to move. Everything is then ground flush so no repair telegraphs through the finished surface.

  6. Prime, base, broadcast

    Primer is applied into the open profile and the pigmented base follows inside the primer's recoat window. Flake is broadcast into the wet base until the surface takes no more, then scraped and vacuumed back flat once cured.

  7. Topcoat, cure, hand over

    Clear coats at the specified wet film thickness, with anti-slip additive if quoted. You get written cure gates and a short care sheet. Then the space is yours again, on the schedule and not before it.

Cure gates

Three different numbers, and they matter.

Walking on a floor, putting a shelving unit back on it, and parking a car on it are three separate thresholds. Cutting the third one short is the most common way a good install gets wrecked in week one.

Typical return-to-service windows
SystemFoot trafficFurniture & storageVehicles
Full polyasparticRoughly a dayRoughly two daysTwo to three days
Epoxy base, polyaspartic topOne to two daysTwo to three daysThree to five days
Full epoxy buildOne to two daysThree daysFive to seven days

These are indicative, not a promise

Cure is driven by temperature, humidity and the specific product data sheet for the materials used on your floor. The numbers that count are the ones written into your quote and confirmed on the day. A cold garage in February will be slower than this table.

Your side

Four things that keep a job on schedule.

  • Empty the space completely, the night before. Not the morning of. Grinding starts early and a half-cleared garage costs an hour that comes out of the cure window.
  • Confirm the colour and flake blend early. Once the base coat is mixed, the decision is made.
  • Keep pets and kids out through the cure. Paw prints in a topcoat cannot be spot-repaired invisibly.
  • Be reachable during grinding. That is when hidden slab conditions appear and when a fast decision saves a day.

Winter work

Cold-weather installs, honestly

Polyaspartic chemistry genuinely extends the season, and we do install through Vaughan winters. Three conditions still have to hold: the slab above the product's minimum application temperature, the slab above dew point so moisture does not condense onto the surface, and enough heat retained through the full cure window.

If a garage cannot be sealed and heated enough to hold those, the answer is to wait. Installing anyway produces a floor that looks fine for a month and then delaminates.

More on fast-cure and cold-tolerant systems

Questions we actually get

How the work gets done.

How much dust does grinding make?
A lot, if it is done badly. Every grinder runs on a HEPA-rated dust extractor and the work area is closed off with poly barriers, which keeps the vast majority of it contained at source. Some fine dust always escapes into an attached garage, so we mask thoroughly and expect to clean afterwards rather than pretending it is a dust-free process.
Can you match a specific colour?
Base coats are pigmented and flake comes in set blends, so we can get close to most targets but cannot guarantee an exact match to a paint chip or a sample from another installer. We show blends in daylight before ordering, because garage lighting is misleading and colour disputes are almost always lighting disputes.
What happens to my old coating?
It gets mechanically removed. If it is loose, it comes up quickly; if it is well bonded, removal is slow and gets quoted as its own line item. Coating over an existing film means inheriting whatever bond that film has to the slab, which is exactly the gamble that produced the failure in the first place.
How long does a finished floor last?
A properly prepared residential garage floor is a long-term surface measured in many years rather than seasons, and the clear topcoat is the part that wears. That layer can be re-coated later without redoing the whole build, provided the base is still sound. Anyone quoting an exact lifespan in years is guessing at your traffic, your climate exposure and your maintenance.
Do you offer a warranty?
Terms are set by whoever holds the contract for your job and are stated in writing in the quote you receive. Ask for them before you sign, and read what is covered, because bond failure, wear, discolouration and hot-tire pickup are not all treated the same way by every warranty.
Can you work while the building stays open?
For commercial floors, usually yes, through phasing or night work. For a residential garage, no. The space has to be empty and closed through the install and the cure, because contamination during cure cannot be undone.